knight-vision-logo In January 2015, Dominican leadership received official approval from the Sinsinawa Dominicans to complete all Knight Vision campaign projects within the year. This page will be updated throughout the construction process so stop by often! Publications and Newsletters July 2014 Summer Magazine July 2014 Summer Magazine 2014 Honor Roll of Donors2014 Honor Roll of Donors March 2015 Knight Vision E-NewsletterMarch 2015 Knight Vision E-Newsletter
Knight-Vision-2nd-E-BlastMay 2015 Knight Vision E-Newsletter Whitefish-Bay-Now-Ground-Breaking-Article-266x300Whitefish Bay Now article on ground breaking Spectrum Article     Spectrum article on Knight Vision project  
  Sign up for our e-newsletter to receive monthly Knight Vision progress reports! Timeline November 2014 — New Boilers Delivered kv-boilers-deliveredIn November, Dominican received an incredible donation from Potawatomi Hotel and Casino — two five-year-old Bryan Boilers. These boilers are being stored in the school basement until it is time to install them.
May 2015 — Main Entrance and Infrastructure Work Begins kv01_Exterior_View_of_Main_Entrance As of May 4, the main entrance of the school is closed off. Students and visitors will use the doors closest to Silver Spring Drive as an entrance. Our current boilers take up an enormous amount of space and extend from the basement into the first floor of the building. Beginning in May, that space renovation and abatement will begin. Once the boilers can be turned off for the season, the old boilers will be removed, the new boilers will be installed and the first floor space that housed the old boilers will be repurposed for theater dressing rooms.  May 4, 2015 — Ground Breaking Ceremony
Current students at Dominican took part in the ground breaking ceremony

Current students at Dominican took part in the ground breaking ceremony

May 4 marked the official beginning of the Knight Vision Renovation Project with a ground breaking ceremony in the Silver Spring parking lot. Eppstein Uhen Architects, CG Schmidt, current and past students all took part in the ceremony to kick off the project.
Representatives from Eppstein Uhen Architects, CG Schmidt and Dominican High School attended the ceremony

Representatives from Eppstein Uhen Architects, CG Schmidt and Dominican High School attended the ceremony

May – August 2015 — Parking Lot, Front Office, Concourse and Cafeteria Work kv04_View_of_Main_office Immediately following graduation, the school will be closed for renovations. During this time the front office will be relocated, the inner and outer concourses will be renovated, the cafeteria will be updated and bathrooms will be added, the main stairwell, the concourse outside of the gym and the bathrooms near the gym will be remodeled. These projects should be completed for the beginning of the 2015-2016 school year in August. kv03_View_of_Cafeteria kv08_Gym_Concourse September – December 2015 — Auditorium Renovation Begins The auditorium will be closed following a Back to School Mass on August 30th. Throughout the first semester of school, the auditorium will receive new flooring, chairs and doors. Wheelchair accessibility will also be added. The new auditorium will be opened and blessed at a December Liturgy.